RACI matrix
Contents |
[edit] Introduction
A RACI matrix is a form of form of responsibility assignment matrix (RAM) that can be used to help systematically manage a process or project. RACI is an acronym that stands for Responsible, Accountable, Consulted, Informed.
[edit] Assigning roles
These designations can be given to individuals involved in a process:
- Responsible: The person in charge of the process.
- Accountable: The person the responsible person reports to and who must sign off on decisions. NB: Occasionally A is taken to mean 'Assists', that is, someone who assists the responsible person.
- Consulted: People who will be involved in discussions about the process.
- Informed: People who will need to be told about the process.
There can only be one responsible person and one accountable person, but there may be several people who are consulted or informed.
[edit] Clarifying assignments
The correct assignment for individuals can be recorded in the form of a RACI matrix, which gives clarity about the involvement of individuals and helps avoid confusion, duplication, wasted effort and omissions. A RACI matrix can provide more specific information about roles and responsibilities than might be possible with a simple tick-box responsibilities matrix.
This can be particularly useful on design and construction projects where there are a great number of different tasks to be performed by a large number of individuals and organisations who may never have worked together before. Knowing who is responsible for each task, who needs to be consulted and who needs to be informed can be complex, but this is essential to the successful running of the project.
For example, in defining project team roles for the production of Building Information Modelling (BIM) information, PAS 1192-2 suggests that RACI indicators might be used to define project delivery team roles, responsibilities and authority for information delivery post contract-award.
A RACI matrix might form part of a BIM execution plan or a Project Execution Plan (PEP) which sets out the strategy for managing a project. It describes who does what and how, defining the policies, procedures and priorities that will be adopted. RACI indicators are also commonly used in project management software.
NB: Other versions of RACI include:
- RACI supplemented with the letter S to form RASCI (or sometimes RACIS), where S is for 'Support' referring to someone motivating and supporting the team.
- The addition of the letter O in the form CAIRO, where O is 'Out of the loop', referring to someone who is not part of the process.
- CAIROS, where the 'Support' role is added to CAIRO.
- RACI-VS, where V is a 'Verifier', verifying the outcome against requirements, and S is the 'Signatory' signing off on the verifiers decision.
- DACI, where D is the 'Driver'.
[edit] Related articles on Designing Buildings Wiki
- BIM.
- Design responsibility matrix.
- Master information delivery plan.
- Project execution plan.
- Projectisation.
- Project roles table.
- Stakeholder matrix
[edit] External references
- GreyCampus, RACI Matrix: How does it help project managers?
- Responsibility Assignment Matrix (RACI Chart).
- Toolshero, RACI Matrix.
Featured articles and news
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.